Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the rocket domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/erce.energy/staging.erce.energy/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the wordpress-seo domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/erce.energy/staging.erce.energy/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the breadcrumb-navxt domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/erce.energy/staging.erce.energy/wp-includes/functions.php on line 6114
Decision Support for Amulet & Talisman Fields Development (WA-8-L) - ERCE
Oil & Gas

Decision Support for Amulet & Talisman Fields Development (WA-8-L)

Technical Studies

North West Shelf

Offshore

Mainland Western Australia (WA)

Decision Support for Amulet & Talisman Fields Development (WA-8-L)

Kato Energy plan to develop the Amulet oil field and redevelop the abandoned Talisman oil field concurrently using relocatable facilities known as the ‘honeybee production system’.

GET IN TOUCH

Project:

Optimising timing of Talisman start-up to ensure production remains within facility constraints

Outcome:

ERCE reviewed Eclipse Dynamic model for Amulet and converted to tNavigator format to speed-up run times prior to modifying history matches and benchmarking recoveries.

Benefit

ERCE conducted a full range of Design of Experiments (over 200 simulation runs) for Amulet to assess key subsurface uncertainties, including aquifer strength and size and decision for timing of water injection after field start-up.