Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the rocket domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/erce.energy/staging.erce.energy/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the all-in-one-wp-security-and-firewall domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/erce.energy/staging.erce.energy/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the wordpress-seo domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/erce.energy/staging.erce.energy/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the breadcrumb-navxt domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/erce.energy/staging.erce.energy/wp-includes/functions.php on line 6114
Reservoir Modelling - ERCE
Lithium

Reservoir Modelling

Sector

Lithium

Project

New Development

Client Objective

Independent Study for Discussion with the Regulator.

Region

South America

Client Valuation

$600 million

Simulation modelling of a Lithium Brine reservoir to understand injection and mixing effects.

Electrification and energy storage are two critical challenges on the path to global Net Zero. Lithium is a critical element in that journey. Lithium Brine development is an area of increasing interest, in terms of generating new supplies.

GET IN TOUCH

Need:

A lithium brine Operator was in discussions with a regulator regarding brine reinjection and the benefits to operations. They wanted to use numerical simulation to communicate the importance of reinjection.

Project:

ERCE were asked to build a scoping simulation model of the reservoir to investigate the impacts of reinjecting produced water, once lithium has been extracted.

Outcome:

Our work provided insight on the importance of injector producer patterns and spacing, pressure maintenance and dilution effects over time.